Completed: 1st phase of Nesson Crude Oil and Produced Water Gathering System in the Bakken

Pipeline
Source: DollarPhotoClub

Enable Midstream Partners, LP (NYSE:ENBL) announced today that the first phase of its Nesson Crude & Produced Water Gathering System is operational. The pipeline serves wells located in Williams and Mountrail Counties of North Dakota, in the prolific Bakken shale play.

Construction of the first segment of the Nesson system began in July 2014. It provides services to producer XTO Energy Inc. and has a maximum throughput of 1,800 bpd. As of May 7, crude oil has been flowing into the downstream delivery pipeline system.

Phase two construction began in April 2015 and is expected to be complete in the fourth quarter of 2015. Maximum throughput for the entire Nesson system is expected to be 30,000 bpd with more than 160 miles of pipeline and 69 origin points to gather crude oil and produced water.

“Our customers continue to have a need for the delivery of energy to key markets,” said Enable Midstream President and CEO Lynn Bourdon. “We have a proven track record of effectively and efficiently deploying capital to meet that need.”

Enable Midstream currently owns around 11,900 miles of gathering pipelines, 13 major processing plants with approximately 2.3 billion cubic feet per day of processing capacity, approximately 7,900 miles of interstate pipelines (including Southeast Supply Header, LLC of which the company owns 49.90 percent), approximately 2,300 miles of intrastate pipelines and eight storage facilities comprising 87.5 billion cubic feet of storage capacity.

Article continues below this message

Have your opinion heard with Shale Gas International

We accept interesting, well-written opinion and analysis articles of up to 1,500 words, that offer unique insights into the shale industry. The articles cannot be overtly promotional in nature and need to fit into at least one of our content categories.

If accepted, the article must be exclusive to Shale Gas International website and cannot appear on any other websites, publications, etc. Each article may contain up to three links to external websites relevant to the content discussed in the piece.

If you would like to contribute to Shale Gas International website, please contact us at: editor[at]mw-ep.com